Skip to main content
Mark Tivey · Licensed CGC1511598 · Veteran-Owned Since 1988(904) 850-6070

Bathroom Remodel Timeline in NE Florida: Week-by-Week from Mark's Walkthrough

1130 words
Share this article:
Bathroom remodel in progress in Northeast Florida

Most homeowners underestimate how long a bathroom remodel takes. The construction itself is 4 to 7 weeks for a standard rebuild. The whole project, including design, permitting, material lead times, and the buffer for what gets discovered, usually runs 8 to 14 weeks elapsed time from contract to final inspection.

Here's what that actually looks like, week by week, from the way Mark sequences a typical NE Florida bathroom project.

Week 0 — The Day-1 walkthrough

Before any contract is signed, Mark walks the bathroom with the homeowner. The walkthrough produces a scope sketch and a punch list of what's likely buried behind the walls.

The walkthrough catches:

  • Vintage of the existing plumbing (cast iron vs. PVC; copper vs. galvanized)
  • Vintage of the existing electrical (aluminum branch wiring is the most common discovery)
  • Slab elevation relative to the rest of the house
  • Vent fan size and termination (is it actually venting outside?)
  • Subfloor condition near the toilet and tub (slow-leak damage is common)
  • HOA constraints if applicable

This produces a cost range and a realistic timeline before any commitment. The homeowner can compare against other contractors with the same information in hand.

Weeks 1–3 — Design and selection

Once a contract is signed, the homeowner makes finish selections: vanity style and counter, fixtures (toilet, tub, shower, faucets), tile (floor, shower walls, accent), paint colors, lighting, mirror, hardware.

Mark's process includes a selection package walkthrough — typically a 2-hour session at the showroom or via virtual review — to make all the decisions before demo starts. This matters more than most homeowners expect: the single biggest schedule risk on a bathroom remodel is the homeowner not making finish decisions early enough.

Custom vanities take 4 to 6 weeks at the cabinet shop. If a custom vanity is in scope, it gets ordered now, against demo, not against install.

Weeks 2–6 — Permit submission and review

Mark submits permits to Clay County (Tyler EPL portal) or Duval County (City of Jacksonville BID) typically in week 2 or 3. Plan review runs 2 to 4 weeks in Clay, 3 to 6 weeks in Duval. The permit usually issues a week or two before construction is scheduled to start.

Permit time runs in parallel with material lead times, so it usually doesn't extend total project elapsed time.

Week 1 of construction — Demo

The first week of construction is demo. Tile comes off the walls and floor. The vanity, toilet, tub, and shower come out. The drywall in the wet areas comes down to expose the studs.

What gets discovered during demo determines how the next four weeks look:

  • Cast-iron drains that need PVC conversion (adds 1 to 2 days)
  • Subfloor damage from old leaks (adds 2 to 4 days plus material)
  • Aluminum branch wiring in the GFCI runs (adds half a day plus material)
  • Mold remediation if the existing waterproofing failed (adds 3 to 7 days plus material)

Mark's contracts include a contingency allowance for these discoveries, sized based on the home's vintage. Pre-1980 NE Florida homes get a 10–15% contingency; pre-1960 homes get 15–20%. The discoveries get itemized at week 1's end, not as week-3 surprises.

Week 2 — Rough plumbing and electrical

Plumbing reroutes happen now (relocating the toilet flange, moving the shower drain, adjusting the supply lines for the new vanity). Slab cuts happen if needed.

Electrical rough-in runs in parallel — new GFCI circuits for the vanity outlets, the vent fan circuit, the lighting circuit, and any new electrical for steam showers or heated floors.

Mechanical rough-in happens at the same time — the vent fan duct gets routed to the exterior, with the proper 110+ CFM unit installed.

The mechanical inspection (vent fan termination) happens at the end of this week.

Week 3 — Insulation, drywall, and waterproofing

Insulation goes in if walls were opened. Cement backer goes up around the tub and shower (cement, not green board). Standard drywall finishes the rest of the walls and ceiling.

The waterproofing layer (Schluter Kerdi membrane or RedGard liquid) goes over the cement backer in the shower. This is a critical step that doesn't get inspected directly but determines the bathroom's lifespan.

Drywall finish (taping, mudding, sanding) takes 3 to 5 days depending on the size of the room.

Week 4 — Tile

Floor tile and shower or tub surround tile go in this week. Layout starts at the focal-point wall and works outward. Tile cuts at the edges are made with a wet saw on site.

Grout follows tile by 24 to 48 hours. Mark spec's epoxy grout in wet areas (showers, tub surrounds) and high-quality cement grout with sealer for the floor.

A standard bathroom takes 4 to 6 days for tile + grout. A premium bathroom with intricate patterns (herringbone, mosaic insets, large-format porcelain) can take 7 to 10 days.

Week 5 — Fixtures and finish

Vanity goes in. Counter template happens (custom counters take 7 to 10 days at the fabricator after template). Plumbing trim — toilet, faucet, shower fixtures, tub fixtures, supply shutoffs. Electrical trim — outlets, switches, lighting fixtures, vent fan grille.

Counter install closes out the week. Mirror, hardware, accessories, and final touches happen in parallel.

The final inspection happens at the end of the week. The Certificate of Completion clears the permit.

What slows things down

Four things consistently extend a bathroom remodel beyond the standard timeline:

Selection decisions made late. If the homeowner is still deciding on tile in week 3, week 4 has nothing to install. Make decisions before demo.

Custom vanity lead time. 4 to 6 weeks at the cabinet shop. Order against demo, not against install.

Premium counter lead time. 2 to 3 weeks at the fabricator after template. Imported stone (Calacatta, Taj Mahal) can be 4 to 6 weeks.

Demo discoveries that exceed contingency. Significant cast-iron drain replacement, major subfloor damage, or unanticipated mold remediation can each add 1 to 2 weeks. Mark's contingency budgeting catches the typical cases; truly anomalous discoveries can still surprise.

Realistic total timeline

Standard bathroom remodel: 8 to 12 weeks contract to final. Premium primary bath: 12 to 18 weeks. With custom vanity + premium imported counter: add 2 to 4 weeks. With layout change requiring slab work: add 1 to 2 weeks.

A 4-to-6 week buffer above the construction-only window is realistic.

Related reading

From Mark Tivey

Ready when you are.

Tell me about your project — you'll see your real budget range mid-flow, and I'll call within 24 hours. No spam, no call center, just me.